Kimberley Estate Bridge (CSR Relocations)
Infrastructure
-
LocationKimberley Estate, 5 Stockwell Drive, Sunbury
-
ClientVillawood
-
Industry SectorInfrastructure, Road and Rail

To facilitate construction of the Kimberley Estate over-rail bridge on the Bendigo Line at Sunbury, approximately 2.5 km of Combined Services Route (CSR) trench was constructed between the existing signalling equipment room at CH 40.175 km and the signal gantry at CH 42.607 km.
The works included multiple under-track bores (UTX) and the relocation of critical V/Line signalling and VicTrack communications cables supporting Bendigo emergency services. Delivered in close collaboration with VicTrack and V/Line, the project achieved compliant design, complex rail interfaces and construction delivery within a record timeframe.
Key Achievements
Delivered on time and within budget, to facilitate timely bridge construction
Delivered with no incidents